Steel casting lays the foundation for development, and innovation-driven development creates the future - the stamping metal parts manufacturing project of Sichuan Liaoyuan Machinery Co., Ltd. is accelerating


Release time:

2025-05-23

Sparks flew and reflected in the sky, and the machinery roared with a powerful sound. Recently, when entering the construction site of the stamping metal parts manufacturing project of Sichuan Liaoyuan Machinery Co., LTD., which is undertaken by Guangxi Zuojiang Science and Industry Construction Co., LTD., a bustling and lively scene comes into view. As an important move in the strategic layout of Sichuan Liaoyuan Machinery Co., LTD., this project is advancing steadily at an accelerated pace. Once completed, it will inject strong impetus into the high-quality development of the enterprise. This project is located on Logistics Avenue, Gaoping District, Nanchong City, Sichuan Province, with a construction land area of 54,029 square meters. The structural form of the production plant is portal steel frame, with 1 floor (with a local mezzanine), measuring 280.5m in length and 120m in width. Building height: The ridge height is 15.2 meters, the eave height is 12.2 meters, and the building area is 34,139.56 square meters.

Since the project broke ground, the project team has faced numerous challenges. First, the site resources are tight. The limited construction area has led to extremely tight material turnover and equipment parking space, posing strict tests to material scheduling and process connection. To this end, the project team plans to divide the fixed material storage area, equipment parking area and construction operation area, and avoid the mixed use of these areas by setting up clear signboards. Materials should be stacked in the order of use. Commonly used materials should be placed close to the construction site to reduce the handling distance. The equipment is parked at staggered times, and the entry and exit are arranged according to the usage time. After the daily construction is completed, clear and recycle reusable materials and tools, and arrange them in the designated area. At the same time, optimize the construction process, adopt segmented flow operation, and alternate different construction sections within the same period of time to reduce the conflict of site occupation caused by the intersection of processes and improve the efficiency of site utilization.

Second, extreme weather frequently disrupted the project. During the project period, there were many heavy rains and strong winds that caused multiple interruptions in high-altitude operations, posing a severe test to the project progress. In the face of rainy weather, the project team formulated a detailed construction emergency plan in advance. Set up rain shelters at the construction site to provide focused protection for the steel structure components under construction and the welding operation areas, ensuring that the welding quality is not affected by rain. Drainage ditches and collection Wells should be reasonably set up within the site, and sufficient drainage equipment should be provided to promptly drain accumulated water and prevent the site from being muddy and affecting the operation of construction machinery and personnel. At the same time, closely monitor the weather forecast, flexibly adjust the construction plan according to the weather changes, and race against time to advance the construction during the intervals of rainfall, such as giving priority to the installation of indoor components and other processes that are not affected by rain.

To ensure the smooth progress of the project, the company has formed a professional project management team to conduct all-round control over aspects such as project quality, progress and safety. In terms of quality control, we strictly adhere to national construction standards for buildings. We conduct rigorous inspections on each batch of building materials and meticulous checks on every construction process to ensure that the project quality meets the standards. In terms of progress management, a detailed construction plan is formulated, with clear time nodes for each stage. A weekly progress report meeting is held to promptly address any issues arising during the construction process and ensure that the project proceeds as planned. Safety management should not be underestimated. Complete safety protection equipment should be provided for construction workers, regular safety training and emergency drills should be carried out, and multiple safety warning signs should be set up at the construction site to constantly remind construction workers to pay attention to safety.

Today, every inch of the project site is pulsating with the pulse of progress. The builders are transforming the lines on the blueprint into solid architectural entities with a meticulous attitude. Their sweat and wisdom are pouring into every detail of this factory building, making a final push for the successful conclusion of the project.

From the blueprint to the completion, the precise welding of every ton of steel and the meticulous polishing of every structure all embody our commitment to quality. This steel structure factory building is not only a perfect blend of industrial aesthetics and architectural mechanics, but also a powerful testament to our commitment fulfilled with professional strength. In the future, we will continue to use innovation as our pen and craftsmanship as our ink to build high-quality projects that stand the test of time for every partner, and jointly write more chapters about quality and trust!

Guangxi Zuojiang Science and Industry Construction Co., Ltd. provides design drawings, offers free detailed drawing services, and undertakes various steel structure factory building projects and sports venue grid structure projects. Welcome to visit our factory. Factory address: No. 59, Airport Avenue, Fusui Economic Zone, Nanning Airport, China-Asean