[ construction progress ] Fangchenggang Anpeida storage base project construction of the latest progress
Release time:
2023-12-26
On December 26, the site of the ANPEIDA storage base in Fangcheng port, which is the general contractor for the construction of Guangxi Zuo River Science and Technology Construction Co. , Ltd. , was very busy, our company has completed 2 # Warehouse Concrete Foundation Foundation Construction Task, is currently the main steel structure hoisting.

Fangcheng Port Anpeida storage base, the total Gross leasable area is 35,122.17 m2.1 # warehouse Gross leasable area is 18,366.81 m2,2 # warehouse Gross leasable area is 16,755.36 m2. The project will make full use of the strategic role of the new land-sea corridor in the western part of the country, building on the regional advantages of Fangchenggang's proximity to ASEAN, and building a warehousing base that integrates sea and land routes, with supply chain services as the entry point, create a smarter, faster, more efficient business ecosystem.

The project has been progressing smoothly since the beginning of construction. According to the construction organization plan, the project team has optimized the construction technology, made detailed construction process, improved construction efficiency, and provided sufficient personnel and machinery, etc. , speed up the progress of Project Construction; our company clear dedicated team to serve the project, timely solve the project problems encountered in the process of advancing, so that the project ran out of“Acceleration.”.